Thursday, November 27, 2008

11/26 Wednesday. Getting ready for stucco!!



Wednesday. 11/26. Garage is insulated, sheetrocked, taped & mudded



Tuesday 11/25 Sheetrock, just need to come in and smooth it out




Friday, November 21, 2008

Finishing up on sheetrock!!

Kitchen

Living Room

Thursday, November 20, 2008

Sheetrock started today!

11/20 Brick is done... Ready for stucco and siding!


Wednesday, November 19, 2008

11/19 More Brick...

Tuesday, November 18, 2008

11/18 They started brick today!!!


Monday, November 17, 2008

Monday 11/17 Sheetrock & Brick is Delivered





Sunday 11/16 Wes, Wes's Dad & I insulate the garage




The house was insulated; sheetrock was being delivered which brought a question to Wes and I... Are they going to insulate the garage? We would like it to be... We did some checked on Saturday night and found out "nope" so this is what we did on Sunday!

Thursday, November 13, 2008

11/13 We have shingles and insulation!!!



Saturday, November 8, 2008

11/05-11/07




Electrician was out :)

Monday, November 3, 2008

Monday, 11/03



Exterior doors and windows are installed! We meet with the Electrican tomorrow :)

Sunday, November 2, 2008

Friday 10/31




Front porch poured, exterior doors and windows delivered!

Wednesday 10/29-Thursday 10/30





Roof has tar paper, fireplace, duct work, gas line and vents are cut out for heating and A/C.